“Rebuild Illinois” Infrastructure Projects Underway In Champaign County

I think it’s fair to say that most driver’s troughout Illinois are tired of crumbling roads. They are sick of potholes. They are frightened of old rickety bridges. If you drive on I-55 from Chicago to Springfield and all the way to St. Louis, there are sections of that highway that are completey unsafe. The same can be said for I-57. Hopefully these complaints will be coming to an end as Illinois Governor JB Pritzker’s infrastructure planned titled “Rebuild Illinois” is taking affect. WCIA recently reported nine projects are either underway or scheduled to start soon throughout Champaign County.

Rebuild Illinois, which was signed into law three years ago by Governor Pritzker is supposed to be an answer to the old roads and bridges throughout the state. Rebuild Illinois is a $45 billion investments in roads, bridges, railroads, universities, early childhood centers and state facilities over six years.

Below are a list of projects in Champaign County, which cost total about $270 million:

  • Interstate 74 bridges over Canadian National Railroad and Market Street in Champaign: Deck repairs began in August of 2020 and are expected to finish this fall. Two lanes of traffic remain open in each direction.
  • Interstate 74 west of St. Joseph: Bridge deck repairs are underway and are expected to be complete in December. There are permanent lane closures with a barrier wall.
  • U.S. Route 150 from County Road 2350 E in St. Joseph to the Vermilion County line: Road resurfacing began this month and will end in September. Intermittent lane closures will occur every day of the project.
  • Interstate 57 from Rantoul to Thomasboro: Resurfacing began this month and will end in December. Daily lane closures will occur.
  • Interstate 57 from Rantoul to the Ford County line: Resurfacing begins in August and will continue into next summer. Daily lane closures will occur.
  • U.S. Route 45 from Saline Branch Ditch to just north of Olympian Drive: Installation of new shoulders and rumble strips will begin in July and will be complete in September. Intermittent lane closures will occur every day of the project.
  • Intersection of U.S. Route 150 and Illinois Route 49 in Ogden: Drainage improvements will begin in August and will end in December. Intermittent lane closures will occur every day of the project.

These projects to repair roads and bridges are incredibly important to the state. They create a safer driving experience for everyone. Hopefully the safer roads and bridges will lead to less traffic accidents and traffic fatalities. An addded bonus is that Rebuild Illinois is also creating thousands of well paying jobs.

If you or a loved one has been seriously injured in a Chicago car crash or Illinois truck accident, then call Illinois personal injury lawyer, Aaron Bryant, for a free legal consultation at 312-614-1076.